Seawater Industry
    Publish time 2025-01-02 08:59    
Seawater Industry

Myanmar Yangon Pilot Station Seawater Desalination and Sewage Integrated Equipment

The project equipment started in October 2018 and was completed in January 2019. It is the general contractor for daily water equipment for the Yangon Pilot Station (20 nautical miles from the coastline) of the Myanmar government.

The project covers 400L/h seawater desalination equipment, 100T/D sewage integration equipment, 144T/h seawater fire diesel pump set (10.8m long shaft, the only domestic manufacturer at that time that could produce long shafts over 10m and shaft end runout coefficient ±1.0mm), 6T/h seawater intake pump set, 6T/h fire electric pressure-stabilizing pump set, 12T/h domestic water supply pump set, air source heat system, and mobile oily sewage treatment equipment.